Working with the draft plans

We got the plans about a week ago with a set sent to our builder, Doug Milholland, and our designer friend, Ann Raab, who is helping with the project.  Today we went over the electric layout with Ann as well as continuing the conversation about heating.  She said that the way they have designed the slab foundation does not work for our soils.  We will talk to Doug about that tomorrow.

Plans are ready

Topsider informed us on Wednesday that our plans have been drawn and would be sent to us Thursday or Friday.  After approval, they will be submitted to the engineer and then to the county.  I am still hoping on being able to pour foundation in August and build the shell in August or September.