Planning the radiant heating

FullSizeRender_1Today we met with Ken of Peninsula Heating along with our contractor, Randy Welle, to discuss his heating plan, decide where to put the manifolds and how and when to get the part done that needed to be done before they add the next layer of gravel.FullSizeRender

He will have folks over next Tuesday morning to lay that conduit. (It is unfortunate that we lose work days because of Memorial Day weekend.)

FullSizeRender_2

.

While they were working, the county building inspector came and checked off the plumbing that was done earlier this week.

.

.It is planned that the electric inspection will be happening next Tuesday afternoon, and then the gravel will come on Wednesday afternoon the gravel trucks will return and then they begin laying the insulation, and hopefully they will be pouring the slab by the following Wednesday, June 3.

Advertisements

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out / Change )

Twitter picture

You are commenting using your Twitter account. Log Out / Change )

Facebook photo

You are commenting using your Facebook account. Log Out / Change )

Google+ photo

You are commenting using your Google+ account. Log Out / Change )

Connecting to %s